The short answer
A complete retaining wall bid gives the length and tallest height, explains how water drains from behind the wall, and spells out what holds it up: the base, the geogrid or rebar, and the block or stone by name. It also says whether the wall needs an engineered design and permit, and who pays for it. Drainage and reinforcement are what keep a wall standing, so if your bid already covers both, you're off to a good start.
Updated November 19, 2026
On this page
What a complete bid spells out
Tick these off against your bid. Anything missing is worth a quick question before you sign.
Vague lines worth a question
“Install retaining wall approx. 40 LF”
Ask for this in writingAsk for the tallest height, how it's measured and the block or stone by name, so the price ties to one specific wall.
“Drainage as needed”
Ask for this in writingAsk for a perforated drain pipe at the base, the gravel behind the wall, filter fabric and where the water will come out.
“Engineering by others”
Ask for this in writingAsk who the "others" are, who hires and pays the engineer, and whether the price can change once the design is done.
“Reinforce per manufacturer”
Ask for this in writingAsk for the number of geogrid layers and their lengths, or the rebar and footing size, written into the scope.
“Restore area”
Ask for this in writingAsk exactly what gets restored, like lawn, beds, sprinkler lines or fencing, and to what condition.
A payment plan tied to finished work
A retaining wall goes up in stages you can see, so tie each payment to one. Keep the deposit modest, or your state's limit, if lower (see deposit limits by state), and hold the last payment until the wall is backfilled and the yard is put back. Our payment schedule checker can test the schedule you were given.
| Stage | Share |
|---|---|
| Deposit at signing | 10% |
| Engineered design done and permit issued (if needed) | 10% |
| Excavation, base pad and first row set | 25% |
| Wall at full height with drain pipe, gravel and reinforcement in | 35% |
| Cap stones on, soil hauled away and yard restored | Balance |
Comparing two or three bids
- Compare the tallest height and how each contractor measured it. Two bids for the same wall may be pricing different heights.
- Check that every bid includes a drain pipe, gravel backfill and filter fabric. A bid without them isn't a cheaper version of the same wall.
- Line up the reinforcement: geogrid layers and lengths, or rebar and footing size.
- See who handles engineering, the permit, the survey and the utility locate in each bid, and add any missing cost to that bid.
- Compare soil haul-off and yard restoration, since those can be a big part of the job.
- Our guide on why contractor bids vary helps explain the gaps, and you can run a free bid check on each bid.
Questions to ask before you sign
- 1Does this wall need an engineered design, and who will get it?
- 2How are you measuring the wall's height?
- 3Where will the water from the drain pipe go?
- 4How many geogrid layers will you use, and how far back will they run?
- 5What block or stone are you using, and how tall can it go without engineering?
- 6Who confirms the property line and calls 811 before you dig?
- 7How will your equipment reach the work area, and what gets restored afterward?
- 8What does your warranty cover if the wall leans or bulges?
Permits
Taller walls, and walls that hold up a driveway, slope or building, often need a permit and an engineered design, while short garden walls often don't. Check with your city or county building department, and have your licensed contractor pull any permit (see who's responsible for permits).
Want a second set of eyes on your bid?
Upload your bid, a PDF or phone photos, and see in about a minute what it leaves out or leaves vague, quoted from your own pages. Free, no account.
Common questions
Does a retaining wall need an engineer?
It depends on the height, the soil and what the wall holds up. Many areas ask for an engineered design once a wall passes a certain height, or when there's a driveway, slope or building above it. Ask your building department, and ask the contractor to say in writing whether your wall needs one.
Should a retaining wall quote include drainage?
Yes. A complete bid lists a perforated drain pipe at the base, clean gravel backfill, filter fabric and where the water comes out. If drainage isn't spelled out, ask for it before you compare prices.
What is geogrid, and how much should a bid include?
Geogrid is a mesh laid between rows of block that runs back into the soil and ties the wall to the hill behind it. The number of layers and their length depend on the wall's height and the block maker's guide or the engineer's design. Ask the bid to list both.
Who's responsible if my retaining wall starts leaning?
That depends on the warranty and what caused it. A bid with a written warranty against leaning, bulging and settling makes it much easier to sort out. If it's already happening, start with what to do when a contractor won't fix mistakes.
Why is one retaining wall bid so much lower?
Often the lower bid leaves something out, like drainage, engineering, soil haul-off or restoration, or it prices a shorter wall. Line up the scope item by item before you decide. A lower bid can still be a good deal once you confirm it covers the same work.
Related reading
These checklists describe common trade practice for a complete bid, not legal requirements. Rules vary by state and city.