Delays and permits

Who is responsible for getting permits, me or the contractor?

The short answer

Your odds: Depends on the facts

Usually the licensed contractor doing the work pulls the permit, and many contracts say so, but the answer turns on your contract, your local building department and your state's rules. Even when the contractor is responsible, the city often looks to you as the owner if work is done without a permit, so put the permit duty in writing and confirm the permit exists before work starts.

Steps to take
6
Laws and cases cited
5
Last checked

What to know

  • Your local building department decides what needs a permit and who may apply for one.
  • Contracts commonly make the contractor responsible for permits, and some states require the contract to say so.
  • Pulling a permit in your own name can make you the responsible party as owner-builder.
  • Some state recovery funds may not cover you if you pulled the permit yourself.
  • Check the permit record for your address before work starts and before the final payment.
On this page
  1. The short answer
  2. How it works in your state
  3. The risk of pulling the permit yourself
  4. What courts have said
  5. How to protect yourself
  6. Your state's rules, with sources
  7. What to gather
  8. What to do, step by step
  9. When to talk to a lawyer now
  10. Common follow-up questions
  11. Laws and cases on this page

The law, in detailTap a topic to open it.

The short answer

In practice, the contractor doing the work usually applies for the permit, because many building departments want a licensed or registered contractor named on it, and the contractor knows the plans. Your contract is where the duty is set. If it says the contractor will obtain all permits, that is a promise you can enforce. If the contract is silent, the answer depends on custom, your local rules and your state's contractor laws, which vary by state.

As the owner, though, you are rarely fully off the hook. The work is on your property, and building departments often deal with the owner when unpermitted work turns up. That is why it pays to settle the permit question in writing before anyone starts, and to check the permit yourself. Permits exist so an inspector checks the work at key stages, such as before walls are closed. Skipping them can leave wiring, plumbing or framing problems that nobody checked, and it can complicate insurance claims and a future sale. A contractor who suggests skipping the permit to save you money is shifting that risk onto you.

  • Read the contract for a permit clause
  • Ask the building department who may apply
  • Confirm the permit is issued before work starts
  • Keep the permit and inspection records

How it works in your state

Some states answer the question directly. In Florida, a contractor who takes more than 10 percent of the price up front on a home job must apply for any needed permits within 30 days and start work within 90 days after they issue[1]. That rule assumes the contractor is the one applying. State rules show that Massachusetts requires the home improvement contract to list the permits needed and say the contractor is responsible for getting them, and that Nevada requires the contractor to apply for and obtain all necessary permits.

Other states tie permits to licensing. State rules show that Wisconsin requires a Dwelling Contractor certification to get building permits for one- and two-family homes, with an exception for an owner who lives or will live in the home and pulls the permit for their own work. Hawaii requires a state contractor license for any job that needs a building permit, and West Virginia and Mississippi do not allow a permit to be issued to someone who needs a license and lacks one. Indiana requires the contract to say the work depends on getting any needed permit, with no work until it is obtained.

Pick your state below to see its contract rules, your licensing board and whether a recovery fund is available.

The risk of pulling the permit yourself

Some contractors ask the homeowner to pull the permit as an owner-builder. That can be a red flag, especially if the contractor is unlicensed or its license does not cover the work. When you pull the permit as owner, you may be treated as the person responsible for the work and for meeting code, and you can lose protections tied to hiring a licensed contractor. See when a contractor pulls the permit in your name.

Recovery funds show the cost. North Carolina's Homeowners Recovery Fund rules say that if you pulled the permit in your own name, you may not qualify unless you used a general contractor[2]. Massachusetts rules say its Guaranty Fund requires that the contractor, not you, pulled the permit. If your contractor wants you on the permit, ask why in writing and check its license; see what to do if you hired an unlicensed contractor.

What courts have said

Who must pull permits is usually set by local rules and your contract, not by a court ruling. A New Jersey case shows what can happen when a contractor skips them. An 82-year-old homeowner's kitchen remodel was poorly done and done without required permits, and the New Jersey Supreme Court held that breaking the state's home improvement regulations is an unlawful practice under the Consumer Fraud Act even without intent to deceive, allowing triple damages and attorney fees for a proven money loss[3]. Other states' consumer laws differ.

Licensing boards can also act on the code problems that often follow skipped permits. In Arizona, the Registrar of Contractors can suspend or revoke a license for materially violating building codes[4].

How to protect yourself

Before you sign, make sure the contract says who will obtain and pay for each permit and who will schedule inspections. Before work starts, look up the permit for your address on your building department's site, or ask to see the permit card posted at the job. Ask the contractor for a copy of each inspection result as the job moves along, and tie the final payment to a passed final inspection. The FTC also advises against making the final payment until the work is done and you are satisfied[5].

If you find that no permit was pulled, act quickly and read what to do when your contractor didn't pull a permit. If you are selling and earlier work was never permitted, see unpermitted work when you sell. If a job fails inspection, see who pays when work fails inspection.

Your state's rules, with sources

Pick your state to see the rules that matter here, each linked to its official source.

What to gather

Tick things off as you collect them. Your list stays on this device only.

0 of 7 gathered

What to do, step by step

  1. 1

    Read the permit clause

    Find who must obtain and pay for permits and schedule inspections. If there is no clause, ask for one in writing.

  2. 2

    Call your building department

    Ask what permits the job needs and who may apply. Note the name of the person you spoke with and the date.

  3. 3

    Check the contractor's license

    Confirm the license covers the work. In some states, a permit cannot be issued to someone who needs a license and lacks one.

  4. 4

    Think twice before signing as owner-builder

    If the contractor asks you to pull the permit, ask why in writing and consider what protections you may give up.

  5. 5

    Verify before work and before final payment

    Look up the permit status before demolition starts, and tie the last payment to a passed final inspection.

  6. 6

    Escalate if the contractor skipped it

    Send a written demand to get the permit and cover the costs. OwnersBack Dispute Prep can organize your records into a dated timeline, evidence index and a demand letter you send in your own name.

When to talk to a lawyer now

  • You were asked to sign as owner-builder for work you are not doing yourself
  • The city has cited you for unpermitted work
  • A sale or refinance depends on legalizing past work
  • The contractor refuses to get a permit it agreed to get
Find a lawyer in your state

Turn this into a plan you can act on

We turn your paperwork, photos and messages into a dated timeline, an evidence index, a step-by-step plan and a demand letter. A person on our team checks every one.

Hiring someone new to finish the job? Check their bid for free before you sign.

Common follow-up questions

Can a homeowner pull their own permit?

Often yes, for work on a home you own, but the rules vary by place. In Wisconsin, for example, an owner who lives or will live in the home may pull a permit for their own work. Pulling it yourself usually makes you responsible for the work and the inspections.

Why would a contractor ask me to pull the permit?

Sometimes for convenience, but sometimes because the contractor lacks the license the permit requires. Check the license first and ask for the reason in writing.

Who pays for the permit?

Whoever the contract says. Many contractors include permit fees in the price. If the contractor applied, ask for the receipt so you know what you were charged.

Is it illegal for a contractor to work without a required permit?

It usually violates local building rules, and in some states it also counts against the contractor under licensing or consumer laws. In New Jersey, violations of home improvement regulations, including working without required permits, supported a Consumer Fraud Act claim[3].

What if my contract doesn't mention permits?

Ask the contractor to add a written permit clause before work starts. If work has already started, ask in writing who applied for the permit and request the permit number.

Laws and cases on this page

Each one was read on its source and checked on November 19, 2026.

  1. 1

    Statute · FL

    Fla. Stat. § 489.126

    What it says

    In Florida, a contractor who takes more than 10 percent of the price up front on a home job must apply for permits within 30 days and start work within 90 days after the permits issue, and a contractor holding more money than the work is worth may not stop work for 90 days without just cause. Doing so with the required intent is a crime, from a misdemeanor under $1,000 up to a first-degree felony at $200,000 or more, and failing to refund within 30 days of your written demand can be used to show intent.

    Keep in mind: Florida only. This is a criminal statute: prosecutors decide whether to charge, and the state must prove intent. Your written demand should go by certified mail as the statute describes.

  2. 2

    Statute · NC

    N.C. Gen. Stat. § 87-15.8 (Homeowners Recovery Fund)

    What it says

    North Carolina's Homeowners Recovery Fund, run by the general contractors licensing board, can reimburse a homeowner who suffered a loss in building or altering a single-family home they own or owned. You generally must first exhaust your legal remedies against the general contractor and hold an unpaid judgment, unless a bankruptcy stay prevents suing.

    Keep in mind: North Carolina only, for single-family homes. Payment is at the board's discretion, not a right, and the board does not pay attorney fees. If you pulled the permit in your own name you may not qualify unless you used a general contractor.

  3. 3

    Court decision · NJ · Supreme Court of New Jersey

    Cox v. Sears Roebuck & Co., 138 N.J. 2, 647 A.2d 454 (1994)

    What it says

    An 82-year-old homeowner hired a large retailer to remodel the kitchen, and the work was poorly done and done without required permits. The New Jersey Supreme Court held that breaking the state's home improvement regulations is an unlawful practice under the Consumer Fraud Act even without intent to deceive, and a homeowner who proves a money loss gets triple damages plus attorney fees; even without a provable loss, the homeowner may recover reasonable attorney fees and costs.

    Keep in mind: New Jersey case under the New Jersey Consumer Fraud Act and its home improvement regulations. Here the repair cost of $6,830 was trebled to $20,490. Other states' consumer laws differ, and many do not make triple damages automatic.

  4. 4

    Statute · AZ

    Ariz. Rev. Stat. § 32-1154

    What it says

    In Arizona, the Registrar of Contractors can suspend or revoke a license for abandoning a contract without legal excuse, for departing from plans or specifications in a material way without the owner's consent, and for materially violating building codes. A complaint that a contractor failed to work in a professional and workmanlike manner can trigger an investigation.

    Keep in mind: This section is about license discipline by the state, not a private lawsuit for money. The Registrar can suspend or revoke a license and, for some violations, impose civil penalties. Deadlines for filing a complaint are not in this section, so check the Registrar's complaint rules (A.R.S. § 32-1155) before relying on it.

  5. 5

    Official guidance · Federal

    FTC consumer guide: How To Avoid a Home Improvement Scam

    What it says

    The FTC warns that demands for full payment up front or cash only, pressure for an immediate decision, and contractors who knock on your door because they are "in the area" are signs of a scam. It advises getting a written contract even if your state does not require one, never paying the full amount up front, and not making the final payment until the work is done and you are satisfied.

    Keep in mind: This is consumer guidance, not a law you can sue under. If you cannot resolve a problem with the contractor, the FTC suggests contacting your state attorney general or local consumer protection office.

Legal information, not legal advice

This page explains the law in general terms so you can understand your options. It isn't legal advice for your situation, and reading it doesn't create an attorney-client relationship. Laws change and differ by state, and the facts of your case matter. OwnersBack isn't a law firm. Before you sue, sign a settlement, or miss a deadline, talk to a licensed attorney in your state.