The short answer
A good garage or ADU bid says who pays for plans, permits and impact or utility fees, shows the building on a site plan with setbacks, and spells out how water, sewer and power reach it. It also lists the foundation, framing and finish specs with allowances, and holds the last payment until the final sign-off or certificate of occupancy. Fees and utility runs are where these bids differ most, so get them in writing first.
Updated November 19, 2026
On this page
What a complete bid spells out
Tick these off against your bid. Anything missing is worth a quick question before you sign.
Vague lines worth a question
“Utility connections by others”
Ask for this in writingAsk who the others are, what the connections will likely involve, and whether any trenching or panel work is in this bid.
“Permit fees not included”
Ask for this in writingAsk for a written list of every expected fee, including impact and utility connection fees, and who pays each one.
“Standard 2-car garage package”
Ask for this in writingAsk for the size, slab thickness, door model, opener, outlets and lighting, so you know what standard includes.
“ADU finishes, builder grade”
Ask for this in writingAsk for the named products or an allowance amount for flooring, cabinets, counters, fixtures and appliances.
A payment plan tied to finished work
For a garage or ADU, tie each payment to an inspection, and keep the last one until the final sign-off or certificate of occupancy. Keep the deposit modest, or your state's limit, if lower. Our payment schedule checker shows whether a schedule stays behind the work.
| Stage | Share |
|---|---|
| Deposit at signing | 10% |
| Foundation and underground utilities inspected | 20% |
| Framing, roof and windows done, framing inspection passed | 25% |
| Rough plumbing, electrical and mechanical pass inspection | 20% |
| Drywall, finishes and fixtures installed | 15% |
| Final sign-off or certificate of occupancy issued | Balance |
Comparing two or three bids
- Check which bids include impact, utility and permit fees, since leaving them out can make one bid look much lower.
- Line up the utility plans, including trench length, sewer connection and meters, because those vary a lot by site.
- Compare the foundation, slab and framing specs, so you're pricing the same building.
- For an ADU, compare the kitchen, bath and heating allowances against what you'd actually install.
- Put it all in our bid comparison spreadsheet, or run a free bid check to see what's missing.
Questions to ask before you sign
- 1Which fees do you expect, and which are in your price?
- 2Have you checked the setbacks and size limits for my lot?
- 3How will water, sewer and power get to the building, and can my main panel handle it?
- 4Are we planning separate meters, and who works with the utility on that?
- 5Have you built ADUs or garages in this city before?
- 6Does the final payment wait for the certificate of occupancy?
- 7How long from permit to move-in, and what usually holds it up?
Permits
New garages and ADUs commonly need a building permit plus electrical, plumbing and mechanical permits, and an ADU may need zoning review before anything else. Check with your city or county building department, and have the licensed contractor pull the permits and schedule the inspections.
Want a second set of eyes on your bid?
Upload your bid, a PDF or phone photos, and see in about a minute what it leaves out or leaves vague, quoted from your own pages. Free, no account.
Common questions
Should an ADU bid include impact and utility fees?
It should at least list them and say who pays. Some contractors include them, and some leave them to you. Either way, get the list in writing so you can compare the real total.
What does a garage bid usually leave out?
Common gaps are the driveway apron, electrical for the door opener and outlets, gutters and site restoration. Ask for each one to be listed as included or not.
When should I make the last payment on an ADU?
Tie it to the final inspection or certificate of occupancy, plus a finished punch list. That sign-off is what makes the unit ready to live in.
Do I need a separate meter for my ADU?
It depends on your city, your utility and how you plan to use the unit. Ask the contractor and your utility early, and get the plan in the bid, since it changes the cost.
What if the contractor says I should pull the permit?
Usually the licensed contractor pulls it, since they're responsible for the work. Here's more on who's responsible for permits.
Related reading
These checklists describe common trade practice for a complete bid, not legal requirements. Rules vary by state and city.