Halfway through building their house, Hannah and Derek got a call from the framer. He hadn’t been paid.
They had already paid the framing draw. Now the framer said the money never reached him. Here’s how Hannah and Derek kept the next draw from going the same way.
5 min read
This is a composite story, built from common situations homeowners describe. Names and details are illustrative.
On this page
A custom home and a draw schedule
Hannah and Derek were building a house on a lot they owned. Their builder’s contract was $412,000, paid in draws at set stages: foundation, framing, dry-in, drywall and so on. Each draw was paid after the builder sent an invoice for that stage.
The framing went up fast and looked solid. They paid the framing draw, and the job moved on to the roof and windows.
A phone call nobody expected
Two months later, the owner of the framing company called. He’d gotten their number from the permit. He was polite but direct: he was still owed $21,000 for the framing, the builder kept saying the check was coming, and he was looking into a lien.
Hannah and Derek had paid that stage in full. It’s a common surprise. Paying your builder doesn’t always mean the people your builder hired got paid.
The drywall draw was due the next week.
What the contract said about paying the subs
- Payments
- “Owner shall pay each draw within 5 days of Contractor’s invoice for the completed stage.”
- Subcontractors
- “Contractor is responsible for payment of all subcontractors and suppliers.”
The contract made the builder responsible for paying the subs. It didn’t ask for any proof that it happened. There was no mention of lien waivers with each draw.
Georgia’s consumer protection office explains that you can pay in full for a new home and still face a lien from someone you never dealt with, like a framer or a lumber supplier. Its advice is to get interim lien waivers signed each time you make a payment, and an Affidavit of Payment from the contractor at the final payment, saying everyone on the job was paid. You or your contractor can also file a Notice of Commencement in the county real estate records. After that, suppliers and laborers must send you a notice or lose their lien rights.
If a lien is filed in Georgia, it expires in 12 months unless the claimant sues. You can also file a Notice of Contest, which gives the claimant 60 days to sue or the lien lapses. Our Georgia contractor rules page has the details. A Georgia attorney can tell you how they apply to your house.
What to ask
What to ask your builder when a subcontractor says he wasn’t paid
Ask in writing before you pay the next draw. Keep the tone neutral. There may be a simple explanation, and you want it on paper either way.
- Was the framer paid for the work in the framing draw? Can you send proof of payment?
- Can you send a list of every subcontractor and supplier on the job so far?
- Will you include a signed lien waiver from each of them with every draw from now on?
- Would you agree to pay the framer from the next draw with a check made out to both of you?
- Has a Notice of Commencement been filed for our house, and if not, will you file one?
Get it in writing
What to get in writing next time
- A list of subcontractors and suppliers, updated as the job goes.
- Interim lien waivers from the builder and the subs each time you pay a draw.
- An Affidavit of Payment from the builder before the final payment.
- Whether a Notice of Commencement will be filed, and by whom.
- Draws tied to stages that pass inspection, not to invoices alone.
Next step
Hannah and Derek’s next step, and yours
Hannah and Derek held the drywall draw and sent the builder those questions with a reply date. The builder said a slow payment from another job had left the framer short. They agreed to pay the framer from the drywall draw with a two-party check, and the builder sent lien waivers with every draw after that. At closing, they got an Affidavit of Payment.
If a subcontractor has already filed, our pages on a subcontractor lien after you paid the contractor and removing a lien walk through the steps. Lien waivers explained shows what each kind covers. You can also read Kevin’s story about a supplier lien on a patio.
If you’re about to sign a building contract, look for the payment and lien waiver lines first. Our free check shows what a new home contract says about draws and waivers.
Have a bid or contract in hand?
Our Free Bid Check reads it in about a minute and shows the biggest things to ask about, quoted from your own pages. No account needed.
Want a person to read every line?
Bid Review is $99. We check your bid against the 37-item OwnersBack Checklist and your state's rules, a real person on our team signs off, and it's back in two business days.
See Bid ReviewQuestions people ask
Can a subcontractor put a lien on my house if I paid the builder?
In many states, yes. Georgia’s consumer protection office says it’s possible to pay in full and still face a lien from someone your builder hired. Other states limit this in different ways. See liens after paying the contractor.
What is a lien waiver?
It’s a signed form where a contractor, subcontractor or supplier gives up lien rights for work that has been paid. Getting one with each payment helps protect you from liens for work you already paid for. See lien waivers explained.
How long does a lien last in Georgia?
A lien claim in Georgia expires within 12 months unless the claimant files suit. If you file a Notice of Contest, the claimant has 60 days to sue or the lien lapses. A Georgia attorney can help with the timing.
Sources
Rules change. We link to the official source for every rule we mention, so you can check what applies to you.
More stories
General information, not legal advice
These stories share general information to help you ask good questions. They aren't legal advice, and rules vary by state and city. For advice about your situation, talk with a licensed attorney or your state's contractor board.