The short answer
Your odds: Depends on the factsUsually the money it takes to put you where the contract promised: the cost to finish or fix the work, minus anything you still owed, plus some related costs you can prove. Some state laws add more, such as double or triple damages, a penalty or attorney fees. The biggest limits are what your documents can prove and what the contractor can actually pay.
What to know
- The usual measure is the reasonable cost to complete or correct the work, minus any unpaid contract balance.
- For small, innocent mistakes, some courts award only the drop in your home's value instead of the cost to tear out and redo the work.
- Consumer protection laws in some states add double or triple damages and attorney fees.
- Bonds and state recovery funds have caps, so a large judgment may be only partly collectible.
On this page
- The basic rule: put you where the contract promised
- Repair cost or drop in value?
- When the law adds more than your losses
- What you can actually collect
- Mistakes that shrink your recovery
- Your state's rules, with sources
- What to gather
- What to do, step by step
- When to talk to a lawyer now
- Common follow-up questions
- Laws and cases on this page
The law, in detailTap a topic to open it.
The basic rule: put you where the contract promised
In a breach of contract case, the goal is generally to give you the benefit of your bargain, not to punish the contractor. Say you agreed to pay $40,000 for a kitchen, paid $30,000, and another contractor will charge $25,000 to finish and fix it. You will spend $55,000 for a $40,000 kitchen, so your loss is roughly $15,000. The details vary by state, but this math is where most cases start, and it is the same idea behind making the contractor pay to finish.
Courts usually measure completion and repair costs by a fair and reasonable market price, so get written estimates from licensed contractors. In one New York case, homeowners whose contractor stopped work recovered $329,565 for the cost of completing the work and correcting defective work, measured that way[1]. That result turned on the evidence each side presented.
- Money paid for work that was never done
- The reasonable cost to finish the job or correct defective work, beyond the unpaid balance
- Damage the contractor caused to other parts of your home
- Related costs you can document, such as extra rent or storage, where your state allows them
Repair cost or drop in value?
Sometimes the cost to fix a defect is far larger than the harm it causes, and courts handle that in different ways. New York's highest court held that for a small, unintentional deviation (pipe from a different maker than the contract named), the owner's credit was the difference in the home's value, not the cost of tearing out and replacing the work[2]. The Wisconsin Supreme Court let a builder who substantially performed recover the contract price minus the owners' damages, crediting the owners for missing items such as cabinets and gutters, and measured a misplaced wall by any drop in value rather than the cost of moving it[3].
Courts can lean the other way when the breach is deliberate. A divided Minnesota Supreme Court in 1939 held that a company that deliberately failed to grade land as promised owed the reasonable cost of doing the work (upwards of $60,000), not the much smaller value the graded land would have had[4]. That case was a land lease, not a home job, and many courts limit repair costs that are grossly out of proportion. A useful rule of thumb: defects that can be fixed without tearing out a big part of the finished work usually support repair costs, while a fix that means major demolition may get you only the drop in value.
When the law adds more than your losses
Some state laws let you recover more than your actual loss. In New Jersey, a homeowner who proved the contractor broke home improvement regulations had repair costs of $6,830 trebled to $20,490, plus attorney fees[5]. Under the Texas Deceptive Trade Practices Act, you can recover economic damages and, if the conduct was knowing, up to three times those damages plus mental anguish damages, along with attorney fees[6]. Massachusetts allows two to three times your damages for willful or knowing violations or a bad-faith refusal to settle, plus attorney fees[7]. Washington lets a court increase damages up to three times, with the extra amount capped at $25,000[8]. New York's general consumer protection law lets anyone hurt by a deceptive business practice recover actual damages or $50, whichever is greater, and for willful or knowing conduct the court may raise the award to as much as three times actual damages, but that increase is capped at $1,000[9]. Also in New York, false written statements that got you to sign can bring your damages plus a $500 penalty and attorney fees[10].
In California, homeowners whose contractor's license had been suspended recovered everything they paid, with no credit to the contractor for the value of its work[11]. Most states do not have a pay-it-all-back rule that strong. See getting money back from an unlicensed contractor.
Some rules cut the other way. For residential construction defects in Texas, the damages you can recover are limited to the items the statute lists, and rejecting a reasonable settlement offer can cap your recovery[12]. Punitive damages, which are meant to punish, are uncommon in contractor cases and usually require more than a broken contract; the rules vary by state. See recovering attorney fees.
What you can actually collect
Winning a number and collecting it are different things. Bonds are often small and shared among claimants. State recovery funds can help when a licensed contractor cannot pay, but they have caps and exclusions. Florida's fund pays up to $100,000 per claim against a Division I contractor for contracts signed on or after July 1, 2024, and does not pay attorney fees, costs, interest or punitive damages[13]. Maryland's fund pays up to $30,000 per claimant for one contractor, and never more than you paid that contractor[14]. Minnesota's pays an owner up to $100,000 per licensee, limited to actual out-of-pocket loss[15]. Virginia's can pay up to $30,000 for a single transaction and can include court costs and attorney fees[16]. Arizona's pays actual damages up to $30,000[17].
Your choice of court matters too. Small claims limits vary widely, for example up to $12,500 for individuals in California, up to $20,000 in a Texas justice court and under $8,000 in Florida. If your loss is bigger, filing in small claims can mean giving up the amount over the limit. Pick your state in the panel below to see its small claims limit and recovery fund, and see how to collect a judgment.
Mistakes that shrink your recovery
Claiming numbers you cannot prove. Judges award what your documents support. Get written estimates, keep receipts and tie every dollar to a specific problem.
Charging the old contractor for upgrades. If the new contractor installs nicer materials than your original contract called for, a court will usually not make the first contractor pay the difference. Keep the second job's scope matched to the first contract, or track upgrades separately.
Your state's rules, with sources
Pick your state to see the rules that matter here, each linked to its official source.
What to gather
Tick things off as you collect them. Your list stays on this device only.
What to do, step by step
- 1
List every dollar
Make a simple spreadsheet of what you paid, what you still owed under the contract, and what it will cost to finish or fix the work.
- 2
Get written estimates
Ask licensed contractors for itemized estimates that match the original scope. Two or three estimates make your number more believable.
- 3
Check for extra remedies
See whether your state's consumer protection law, licensing law or false-statements law adds damages, a penalty or attorney fees.
- 4
Put the number in a demand
Send the contractor a written demand with your calculation and a deadline. OwnersBack Dispute Prep can organize your records into a dated timeline, evidence index and a demand letter you send in your own name.
- 5
Pick the right court
Compare your total with your state's small claims limit before you file, so you do not give up money you could otherwise claim.
- 6
Plan how you will collect
Look up the contractor's bond and your state's recovery fund rules, and note their caps and deadlines.
When to talk to a lawyer now
- Your loss is well above your state's small claims limit.
- Your state's consumer protection law may allow double or triple damages or attorney fees.
- The fix would require major demolition and the contractor argues you should get only the drop in value.
- The contractor has assets worth pursuing, or has moved them into another company.
Turn this into a plan you can act on
We turn your paperwork, photos and messages into a dated timeline, an evidence index, a step-by-step plan and a demand letter. A person on our team checks every one.
Hiring someone new to finish the job? Check their bid for free before you sign.
Common follow-up questions
Can I get my money back and also make the contractor pay to finish?
Not both in full. Courts generally avoid paying you twice. The usual approach credits what you paid and what you still owed against the cost to finish, so you end up where the contract promised.
Can I sue for stress and inconvenience?
In most contract cases, emotional distress is hard to recover. Some statutes allow it in limited situations, such as mental anguish damages under the Texas Deceptive Trade Practices Act when the conduct was knowing.
Can I get triple damages?
Only where a statute allows it. New Jersey, Texas, Massachusetts and Washington are examples, each with its own conditions, such as proof of a money loss or knowing conduct. New York's general consumer protection law also allows an increase for willful or knowing conduct, but caps that increase at $1,000[9]. Many states do not make triple damages automatic.
Does a recovery fund pay my attorney fees?
It depends on the state. The Florida, Maryland and Minnesota funds do not pay attorney fees, while Virginia's fund can include court costs and attorney fees within its cap.
What if my claim is bigger than the small claims limit?
You can usually file in a higher court for the full amount, or file in small claims and give up the amount over the limit. Compare the time, cost and risk of each before you decide.
Laws and cases on this page
Each one was read on its source and checked on November 19, 2026.
- 1
Court decision · NY · New York Supreme Court, Appellate Division, Second Department
Home Construction Corp. v. Beaury, 2017 NY Slip Op 02628 (App. Div. 2d Dept. 2017)
What it says
A contractor renovating a house worked without a signed contract, then stopped work with the job unfinished. The court dismissed the contractor's claim for more money because it did not prove the value of its work, and it awarded the homeowners $329,565 for the cost of completing the work and correcting defective work, measured by the fair and reasonable market price.
Keep in mind: New York intermediate appellate decision that turned on its facts and the evidence each side presented. New York General Business Law section 771 requires home improvement contracts to be in writing, but the court noted a contractor may still try to recover the reasonable value of its work. Other states may differ.
- 2
Court decision · NY · New York Court of Appeals
Jacob & Youngs, Inc. v. Kent, 230 N.Y. 239 (1921)
What it says
A builder used pipe from a different maker than the contract named, through a subcontractor's oversight, and the owner refused to make the final payment. New York's highest court held that for a small, unintentional deviation like this, the owner's credit is the difference in the home's value, not the cost of tearing out and replacing the work.
Keep in mind: New York case from 1921. The court stressed the default was trivial and not willful; a contractor who deliberately or seriously departs from the contract may be treated differently. Other states may apply different rules.
- 3
Court decision · WI · Supreme Court of Wisconsin
Plante v. Jacobs, 10 Wis. 2d 567, 103 N.W.2d 296 (1960)
What it says
A builder sued homeowners for the unpaid balance on a new house. The court held that 'substantial performance' of a house contract does not require perfection, so the builder could recover the contract price minus the owners' damages, and for a living-room wall built in the wrong place the owners' damages were measured by any drop in the home's value rather than the cost of moving the wall.
Keep in mind: Wisconsin Supreme Court case, and the builder won. It turned on its facts: missing items such as kitchen cabinets and gutters were credited to the owners, while the wall, built more than a foot out of place, was found to cause no loss in market value, and the owners had not asked for it to be fixed during construction. Repair costs are generally allowed for defects that can be fixed without tearing out a substantial part of the finished work; where a fix would mean major demolition, the owner may get only the drop in value. If the contract makes every detail essential, a stricter standard may apply. Other states may differ.
- 4
Court decision · MN · Supreme Court of Minnesota
Groves v. John Wunder Co., 205 Minn. 163, 286 N.W. 235 (1939)
What it says
A company deliberately failed to leave land at the even grade it had promised. The court held that the proper measure of damages is the reasonable cost of doing the promised work (upwards of $60,000), not the value the land would have had once graded (about $12,160), and ordered a new trial.
Keep in mind: Minnesota case from 1939 about a land lease for removing sand and gravel, not a home improvement job, and the breach was deliberate. A divided court decided it: two justices did not take part, and the dissent noted the prevailing opinion was a minority of the full court. Many courts limit repair or completion costs when they are grossly out of proportion to the benefit. Other states may differ.
- 5
Court decision · NJ · Supreme Court of New Jersey
Cox v. Sears Roebuck & Co., 138 N.J. 2, 647 A.2d 454 (1994)
What it says
An 82-year-old homeowner hired a large retailer to remodel the kitchen, and the work was poorly done and done without required permits. The New Jersey Supreme Court held that breaking the state's home improvement regulations is an unlawful practice under the Consumer Fraud Act even without intent to deceive, and a homeowner who proves a money loss gets triple damages plus attorney fees; even without a provable loss, the homeowner may recover reasonable attorney fees and costs.
Keep in mind: New Jersey case under the New Jersey Consumer Fraud Act and its home improvement regulations. Here the repair cost of $6,830 was trebled to $20,490. Other states' consumer laws differ, and many do not make triple damages automatic.
- 6
Statute · TX
Tex. Bus. & Com. Code § 17.50 (Deceptive Trade Practices Act)
What it says
Under the Texas Deceptive Trade Practices Act, a consumer harmed by deceptive conduct can recover economic damages, and up to three times those damages plus mental anguish damages if the conduct was knowing. A consumer who wins is awarded court costs and reasonable attorney fees, and you generally must give written notice at least 60 days before suing.
Keep in mind: Texas only. The 60-day notice rule is in § 17.505, not § 17.50. For residential construction defects, Texas Property Code chapter 27 controls wherever it conflicts with the DTPA (§ 17.44(b)), and it has its own notice and inspection steps. The Act has exemptions (§ 17.49), for example for professional advice, so check that your claim fits; the large-contract exemptions do not apply to claims about your own residence.
- 7
Statute · MA
Mass. Gen. Laws ch. 93A, § 9
What it says
Under the Massachusetts consumer protection law, you must send a written demand for relief at least 30 days before suing over an unfair or deceptive practice. If you win you get your actual damages or $25, whichever is more, the court can award two to three times that amount for willful or knowing violations or a bad-faith refusal to settle, and you recover reasonable attorney fees.
Keep in mind: Massachusetts only. The 30-day demand is not required for a counterclaim or cross-claim, or if the contractor has no place of business and keeps no assets in Massachusetts. If the contractor makes a reasonable written settlement offer within 30 days and you reject it, your recovery can be limited to that offer and fees after the rejection may not be recovered.
- 8
Statute · WA
Wash. Rev. Code § 19.86.090
What it says
Under Washington's Consumer Protection Act, a person hurt by an unfair or deceptive business practice can sue for actual damages plus court costs and a reasonable attorney fee. The court may also increase the damages up to three times the actual damages, with the extra amount capped at $25,000.
Keep in mind: Washington law only. You must still prove all the CPA elements (see Hangman Ridge). Other states have their own consumer laws with different damage multipliers and fee rules.
- 9
Statute · NY
N.Y. Gen. Bus. Law § 349
What it says
New York's consumer protection law lets anyone hurt by a deceptive business practice sue for actual damages or $50, whichever is greater. If the business acted willfully or knowingly, the court may raise the award up to three times actual damages, capped at $1,000, and may award reasonable attorney's fees to a winning plaintiff.
Keep in mind: The current text also bans "unfair" and "abusive" practices, but the private lawsuit in subdivision (h) is written for deceptive acts or practices. The treble increase is capped at $1,000, so it helps most with smaller losses; it is in addition to, not a replacement for, a breach of contract claim.
- 10
Statute · NY
N.Y. Gen. Bus. Law § 772
What it says
In New York, a homeowner who was talked into a home improvement contract by a contractor's false or fraudulent written statements can recover their damages plus a $500 penalty and reasonable attorney fees.
Keep in mind: New York only, and the false statements must be in writing. If the court finds the homeowner's suit had no arguable merit, it can order the homeowner to pay the contractor's attorney fees.
- 11
Court decision · CA · California Court of Appeal, Fifth Appellate District
White v. Cridlebaugh, 178 Cal. App. 4th 506 (2009)
What it says
Homeowners sued a builder whose license had been suspended because it no longer had a qualifying licensed individual. The court held that under California Business and Professions Code section 7031(b), the homeowners could recover everything they paid, and the contractor could not subtract the value of the work or materials it provided.
Keep in mind: California appellate case applying a California statute. The refund judgment ran only against the contractor's corporation; the individuals who ran it were not held personally liable in this case. Section 7031(b) does not apply if the narrow 'substantial compliance' exception for licensing is met. Most states do not have a 'pay it all back' rule this strong; check your own state's law.
- 12
Statute · TX
Tex. Prop. Code § 27.004
What it says
Under the Texas Residential Construction Liability Act, you must send the contractor written notice of the defects by certified mail, return receipt requested, at least 60 days before suing. The contractor gets a chance to inspect within 35 days and may make a written settlement offer within 60 days of your notice.
Keep in mind: Texas only, for residential construction defects. If you skip the notice or inspection steps, the case can be abated (paused). Notice is excused if you must sue sooner to beat the statute of limitations or are raising the defect as a counterclaim. If you reject a reasonable settlement offer, your recovery is capped at the value of the contractor's last offer plus costs and attorney fees incurred before you rejected it. The damages you can recover are limited to the items the statute lists, such as reasonable repair costs.
- 13
Statute · FL
Fla. Stat. § 489.143
What it says
For Florida contracts signed on or after July 1, 2024, the recovery fund pays up to $100,000 per claim against a Division I contractor and up to $30,000 per claim against a Division II contractor. Payment is limited to actual damages, and attorney fees, court costs, interest and punitive damages are not paid by the fund.
Keep in mind: The fund pays only after you have a judgment, arbitration award or restitution order against the contractor and meet the conditions in Fla. Stat. § 489.141, which is a separate section. Older contracts have lower caps (for example $50,000 per Division I claim for contracts from July 1, 2004 until the 2024 change), and subsection (2) still mentions a $25,000 figure, so confirm the cap for your contract date with the Construction Industry Licensing Board. There are also total caps per contractor ($2 million for a Division I contractor and $600,000 for a Division II contractor on newer contracts), so many victims of the same contractor may share a limited amount.
- 14
Statute · MD
Md. Code, Bus. Reg. § 8-405
What it says
Maryland's Home Improvement Guaranty Fund can pay a homeowner for an actual loss caused by a licensed contractor, up to $30,000 per claimant for one contractor and never more than you paid that contractor. You must file within 3 years after you discovered, or should have discovered, the loss.
Keep in mind: Maryland only, for licensed contractors. You must live in the home or own no more than three residences, and certain relatives, employees, officers and partners of the contractor cannot claim. The fund does not pay attorney fees, court costs, interest, consequential, personal injury or punitive damages. Total awards for one contractor are capped at $250,000 across all claimants unless the contractor repays the fund, and you may have to arbitrate first if your contract requires it.
- 15
Statute · MN
Minn. Stat. § 326B.89
What it says
Minnesota's Contractor Recovery Fund can pay an owner or lessee of a one-to-four family home who contracted directly with a licensed residential contractor or remodeler and holds a final judgment for fraud, deception, dishonest practices, conversion of funds or failure of performance. Payment is up to $100,000 per licensee for an owner, limited to actual out-of-pocket loss, and you must apply within two years after the judgment becomes final.
Keep in mind: Minnesota only, for licensed residential contractors. Attorney fees, litigation costs and interest are not paid, and all owners together are capped at $550,000 per licensee.
- 16
Statute · VA
Va. Code § 54.1-1123
What it says
Virginia's recovery fund can pay part of an unpaid court judgment against a licensed contractor, up to $30,000 for a single transaction, counting anything already paid from the contractor's bond. Court costs and attorney fees can be included, but interest and punitive damages cannot.
Keep in mind: Virginia only. You need a final judgment first. Total payments for one contractor are capped at $100,000 per two-year period, so claims may be prorated if many people file against the same contractor, and the Board may hold payment for up to a year after your judgment if it expects more claims. Other eligibility rules are in § 54.1-1120.
- 17
Statute · AZ
Ariz. Rev. Stat. § 32-1136
What it says
Arizona's recovery fund pays your actual damages, minus anything you recovered from other sources, up to $30,000. An action that may lead to a fund payment must be started no later than two years from the contractor's act that caused the injury or from the date of occupancy.
Keep in mind: Only eligible claimants under A.R.S. § 32-1132 qualify. You need a final judgment against a residential contractor, written notice to the Registrar of Contractors when you start the case and at least 20 days before asking for payment, and you must first go after any contractor bond and show you know of no other assets to pay the judgment. A contractor's spouse cannot recover.
Read next
Legal information, not legal advice
This page explains the law in general terms so you can understand your options. It isn't legal advice for your situation, and reading it doesn't create an attorney-client relationship. Laws change and differ by state, and the facts of your case matter. OwnersBack isn't a law firm. Before you sue, sign a settlement, or miss a deadline, talk to a licensed attorney in your state.