My contractor keeps delaying the job. What can I do?

The short answer

Your odds: Depends on the facts

It depends on your contract and on why the job is late. Delays caused by you, weather, permits or materials that are truly unavailable may be excused, but long, unexplained delays can be a breach of contract and, at some point, abandonment. Your best move is to put the delays and a firm, reasonable deadline in writing now, which sets up your options if the contractor still does not show.

Steps to take
6
Laws and cases cited
8
Last checked

What to know

  • Your contract's start and completion dates are the yardstick, and many states require them in writing.
  • Some delays are excused, such as ones you caused or events outside the contractor's control.
  • A written deadline turns frustration into a clear record of breach.
  • Some states require a refund on written request when no real work has been done long after the start date.
  • In a few states, taking money and not doing the work can become a crime, and your written demand plays a key role.
On this page
  1. Do you have a case?
  2. When delay turns into breach or abandonment
  3. When the money is the real issue
  4. What courts have said
  5. What you can recover
  6. Mistakes that hurt your case
  7. Your state's rules, with sources
  8. What to gather
  9. What to do, step by step
  10. When to talk to a lawyer now
  11. Common follow-up questions
  12. Laws and cases on this page

The law, in detailTap a topic to open it.

Do you have a case?

A delay becomes a legal problem when the contractor misses a deadline it agreed to, or takes far longer than is reasonable when no deadline was set, without a good excuse. You generally need to show the agreed timeline, that the contractor missed it, that the delay was not caused by you or excused by the contract, and that it cost you something, such as extra rent, storage, higher prices, damage from an open roof or the loss of use of your home. This general rule varies by state.

Many states require start and completion dates in the contract itself. In New York, a home improvement contract must list approximate start and completion dates[1]. Connecticut's consumer protection agency says the contract must include the start and completion dates[2]. If your contract has no dates, a court will usually look at what was said, what is reasonable for the work and how the contractor behaved. Contractors often point to one of these excuses:

  • Changes you requested or approved
  • Waiting on your decisions, selections or payments
  • Permit or inspection delays outside its control
  • Severe weather
  • Materials that were truly unavailable

When delay turns into breach or abandonment

A short delay is usually a minor breach: you may claim your actual costs, but you generally still have to let the contractor finish. A long or repeated delay, especially with no communication, can become a material breach that lets you end the contract and hire someone else. If the contractor stops showing up for weeks and stops answering, the job may be legally abandoned; see when a stalled job counts as abandoned and what to do when your contractor stops answering.

Some states draw concrete lines. In Florida, a contractor who takes more than 10 percent up front on a home job must apply for permits within 30 days and start within 90 days after they issue, and a contractor holding more money than the work is worth may not stop work for 90 days without just cause[3]. Florida's licensing board can discipline a contractor for abandoning a job, which is presumed after 90 days without just cause[4]. In Arizona, abandoning a contract without legal excuse is a ground for license discipline[5].

When the money is the real issue

Endless delays sometimes signal that a contractor took your money with no plan to do the work. Several states treat that as a crime. In Illinois, intent for home repair fraud is presumed if the contractor did little or no work, keeps your money and, for example, ignores your written demand to start or finish within 10 days[6]. In Virginia, a contractor who takes an advance with intent to defraud and neither does the work nor returns the money within 15 days of your certified-mail request is guilty of larceny[7]. These are criminal statutes enforced by prosecutors, and the contractor's intent is still at issue (in Illinois the presumption can be rebutted), but your written demand is a key piece of the record.

State rules also give refund rights for jobs that never really got going. Connecticut requires a refund within 10 days of your written request if no substantial part of the work has been done and more than 30 days have passed since the contract's start date, and Pennsylvania has a similar rule at 45 days. Delaware's rules say the contractor must finish by the listed date unless delayed by events beyond its control or you agree in writing to a later date, and Illinois lets you cancel if the contractor does not start or finish on time. Pick your state below to see its rules, licensing board and small claims limit.

What courts have said

When a contractor stops with the job unfinished, the homeowner's recovery often turns on proof. In a New York case, a contractor renovating a house without a signed contract stopped work with the job unfinished. The appeals court rejected the contractor's claim for more money because it did not prove the value of its work, and awarded the homeowners the cost of completing and correcting the work at a fair and reasonable market price[8]. That decision turned on its own facts and evidence, but it shows why your dated records and completion bids matter so much.

What you can recover

If the delay is a breach, you may claim the costs it caused that the contractor could foresee, such as extra rent or storage, temporary repairs to protect the house, and higher costs to finish if prices rose while you waited. If you end the contract over a material delay, you may also claim the extra cost of hiring someone else to finish. Some contracts set a daily amount for late completion; read yours, because it may limit or replace other delay damages. For more, see suing over a missed completion date.

Keep every receipt. A delay claim is only as strong as the numbers behind it.

Mistakes that hurt your case

Avoid complaining only by phone, quietly accepting new dates without writing them down, or firing the contractor before giving a clear written deadline. Also avoid causing delays yourself: make selections on time, keep the site accessible and pay what is properly due. If you are ready to end it, read how to fire your contractor first, and send a demand letter that sets a final date.

Your state's rules, with sources

Pick your state to see the rules that matter here, each linked to its official source.

What to gather

Tick things off as you collect them. Your list stays on this device only.

0 of 8 gathered

What to do, step by step

  1. 1

    Start a delay log today

    Write down each missed day, promised date and excuse, with photos. Keep the log going until the job is done.

  2. 2

    Check the contract dates and delay terms

    Find the start and completion dates, any clause that excuses delays and any daily late amount.

  3. 3

    Send a written deadline

    Ask for a written schedule and a firm, reasonable date to resume and finish. Send it by certified mail as well as email, since in some states a written demand carries legal weight.

  4. 4

    Keep payments in line with the work

    Do not pay ahead of the work. If your contract allows, pay only for work actually done.

  5. 5

    Escalate with a demand letter and complaint

    If the deadline passes, send a demand letter and file with your licensing board. OwnersBack Dispute Prep can organize your log and records into a dated timeline, evidence index and a demand letter you send in your own name.

  6. 6

    End the contract and finish with someone else

    If the delay has become a material breach, send a written termination, get bids and claim the extra cost.

When to talk to a lawyer now

  • The contractor holds a large sum of your money and has not worked in weeks
  • Your home is exposed to weather or unsafe because of the unfinished work
  • You want to end the contract and it has a strict termination or notice clause
  • The contractor threatens a lien or lawsuit if you hire someone else
Find a lawyer in your state

Turn this into a plan you can act on

We turn your paperwork, photos and messages into a dated timeline, an evidence index, a step-by-step plan and a demand letter. A person on our team checks every one.

Hiring someone new to finish the job? Check their bid for free before you sign.

Common follow-up questions

How long is too long for a contractor delay?

There is no single number. Compare the delay to your contract dates and to what is reasonable for the work. Some states draw specific lines, such as Florida's rule against stopping work for 90 days without just cause when the contractor holds more money than the work is worth[3].

Can I fire my contractor for delays?

Often yes, if the delay is long and unexcused and you gave written notice with a fair deadline. Firing too early or without notice can expose you to a claim, so document first.

Can I get money for delays?

You may recover foreseeable costs the delay caused, such as extra rent or storage, if the delay was the contractor's fault. Some contracts set a daily late amount instead.

Is my contractor allowed to work other jobs and leave mine?

Contractors often juggle jobs, and short gaps are common. What matters is whether the contractor meets the contract dates or a reasonable schedule. Ask for a written schedule and hold the contractor to it.

What if the contractor blames permits or materials?

Ask for proof, such as the permit application date or a supplier's backorder notice. Real delays outside the contractor's control may be excused, but they should still be communicated and documented.

Laws and cases on this page

Each one was read on its source and checked on November 19, 2026.

  1. 1

    Statute · NY

    N.Y. Gen. Bus. Law § 771

    What it says

    In New York, a home improvement contract and every change to it must be in writing, signed by all parties, legible and in plain English, and you must get a signed copy before work starts. It must list the contractor's name, address, phone and any license number, approximate start and completion dates, the work and materials, the price, a lien notice, a notice about how your prepayments must be protected, any insurance covering the work, and, if progress payments are used, a schedule tied to stages of work. It must also tell you that you can cancel until midnight of the third business day after signing, except in certain emergencies you started.

    Keep in mind: New York only. This section lists what the contract must contain; what happens when a term is missing depends on the facts and on court decisions.

  2. 2

    Official guidance · CT

    Connecticut home improvement contract requirements (Department of Consumer Protection)

    What it says

    Connecticut's consumer protection agency says a home improvement contract and all changes to it must be in writing, include the contractor's registration number, the signing, start, completion and cancellation dates, the full work and price, and a notice of your right to cancel. Both sides must sign and date it, and you get a signed copy.

    Keep in mind: This is the agency's consumer guidance, not the statute text. It does not say what happens if a term is missing; that is governed by the Home Improvement Act and court decisions.

  3. 3

    Statute · FL

    Fla. Stat. § 489.126

    What it says

    In Florida, a contractor who takes more than 10 percent of the price up front on a home job must apply for permits within 30 days and start work within 90 days after the permits issue, and a contractor holding more money than the work is worth may not stop work for 90 days without just cause. Doing so with the required intent is a crime, from a misdemeanor under $1,000 up to a first-degree felony at $200,000 or more, and failing to refund within 30 days of your written demand can be used to show intent.

    Keep in mind: Florida only. This is a criminal statute: prosecutors decide whether to charge, and the state must prove intent. Your written demand should go by certified mail as the statute describes.

  4. 4

    Statute · FL

    Fla. Stat. § 489.129

    What it says

    Florida's construction licensing board can discipline a contractor, including revoking or suspending the license, fining up to $10,000 per violation, and ordering restitution to the customer. Grounds include abandoning a job (presumed after 90 days without just cause), mismanagement that causes the customer financial harm, and helping an unlicensed person or letting someone else use the license.

    Keep in mind: Florida law only, and it applies to state-certified or registered contractors. Board discipline is separate from a lawsuit for your money. Other states' licensing laws list different grounds and penalties.

  5. 5

    Statute · AZ

    Ariz. Rev. Stat. § 32-1154

    What it says

    In Arizona, the Registrar of Contractors can suspend or revoke a license for abandoning a contract without legal excuse, for departing from plans or specifications in a material way without the owner's consent, and for materially violating building codes. A complaint that a contractor failed to work in a professional and workmanlike manner can trigger an investigation.

    Keep in mind: This section is about license discipline by the state, not a private lawsuit for money. The Registrar can suspend or revoke a license and, for some violations, impose civil penalties. Deadlines for filing a complaint are not in this section, so check the Registrar's complaint rules (A.R.S. § 32-1155) before relying on it.

  6. 6

    Statute · IL

    815 ILCS 515/3 (Home Repair Fraud Act)

    What it says

    In Illinois, home repair fraud includes promising work the contractor does not intend to do, using false promises to get you to sign, requiring an unconscionable price on a contract of $4,000 or more, or damaging your property to get you to hire them. Intent is presumed if the contractor did little or no work, keeps your money, and, for example, ignores your written demand to start or finish within 10 days.

    Keep in mind: Illinois only. This is a criminal statute enforced by prosecutors, and the presumption of intent can be rebutted.

  7. 7

    Statute · VA

    Va. Code § 18.2-200.1

    What it says

    In Virginia, a contractor who takes an advance with intent to defraud, promising to do construction or improvement work, and then neither does the work nor returns the money within 15 days of your certified-mail request, is guilty of larceny.

    Keep in mind: Virginia only. This is a criminal statute: prosecutors decide whether to charge, and fraudulent intent must be proven. Send the request by certified mail, return receipt requested, to the address the statute describes.

  8. 8

    Court decision · NY · New York Supreme Court, Appellate Division, Second Department

    Home Construction Corp. v. Beaury, 2017 NY Slip Op 02628 (App. Div. 2d Dept. 2017)

    What it says

    A contractor renovating a house worked without a signed contract, then stopped work with the job unfinished. The court dismissed the contractor's claim for more money because it did not prove the value of its work, and it awarded the homeowners $329,565 for the cost of completing the work and correcting defective work, measured by the fair and reasonable market price.

    Keep in mind: New York intermediate appellate decision that turned on its facts and the evidence each side presented. New York General Business Law section 771 requires home improvement contracts to be in writing, but the court noted a contractor may still try to recover the reasonable value of its work. Other states may differ.

Legal information, not legal advice

This page explains the law in general terms so you can understand your options. It isn't legal advice for your situation, and reading it doesn't create an attorney-client relationship. Laws change and differ by state, and the facts of your case matter. OwnersBack isn't a law firm. Before you sue, sign a settlement, or miss a deadline, talk to a licensed attorney in your state.