My contractor is charging for changes that were never put in writing

The short answer

Your odds: Depends on the facts

Not automatically. Many states require changes to a home improvement contract to be in writing and signed, and some say an unsigned change can't be enforced against you. But if you asked for the extra work and received it, many courts will still let the contractor recover a reasonable amount for it. Your strongest ground is work you never asked for, or a price you never agreed to.

Steps to take
6
Laws and cases cited
8
Last checked

What to know

  • Many states require every change order to be written and signed by you.
  • Breaking that rule can expose the contractor to board discipline and, in some states, limit what it can collect.
  • Courts often still let a contractor recover the reasonable value of extra work you requested.
  • Work you never asked for, or an inflated price for a small change, is where you can push back hardest.
On this page
  1. Do you have a case?
  2. The legal rules that usually apply
  3. What courts have said
  4. How it works in your state
  5. Mistakes that hurt your case
  6. Your state's rules, with sources
  7. What to gather
  8. What to do, step by step
  9. When to talk to a lawyer now
  10. Common follow-up questions
  11. Laws and cases on this page

The law, in detailTap a topic to open it.

Do you have a case?

Unwritten changes are one of the most common sources of contractor billing fights. A conversation on site, a quick yes by text, an assumption that a fix was free, and then a bill arrives with charges you never saw coming. Whether you have to pay turns on three things. Did you ask for the change? Did anyone agree on a price? And what does your state's law say about changes that aren't in writing?

Sort the charges into groups. Work you never requested is the easiest to dispute. Work you requested without discussing price is often owed at a reasonable value, not whatever the contractor names. Work that was already in the original scope, but is being billed as extra, should not be charged twice. Also check the contract itself. Many contracts include their own change order clause that says how changes must be approved, and a contractor who ignored its own clause has a harder time insisting you pay.

  • You never asked for the work being billed as extra.
  • No one told you the price before the work was done.
  • The charge covers work already included in the original contract.
  • Your state requires changes to be written and signed, and this one wasn't.

What courts have said

Courts disagree on how far the writing rule protects you. In Connecticut, the Supreme Court held that a home improvement contract that did not meet the state's Home Improvement Act could not be enforced against the homeowner, and the contractor could not recover the value of its work through unjust enrichment either[4]. Pennsylvania's law says a home improvement contract is not valid or enforceable against the homeowner unless it meets the law's requirements, such as being in writing and signed by both sides[5]. Even so, Pennsylvania's Supreme Court held that a contractor with a noncompliant contract could still sue for the reasonable value of its work[6].

Even in Connecticut, the protection has limits. The same court later held that a homeowner who acts in bad faith cannot hide behind the Act, in a case where the homeowner tried to avoid paying for extra work the homeowner had requested[7]. And a New York appellate court noted that, although New York requires home improvement contracts to be in writing, a contractor may still try to recover the reasonable value of its work; in that case the contractor's claim failed because it did not prove that value[8].

How it works in your state

Pick your state below to see its change order rules. Some are strict. Indiana does not let a change be enforced against you unless it is written and signed by you. In Nevada, a change order is unenforceable unless it shows all changes in scope and price and you accept it. Virginia treats a licensed contractor's failure to get a signed written change order as a prohibited act, and Pennsylvania bars a contractor from changing the plans or specifications without a written change order, signed by both of you, that states the price change.

A broken change order rule is often a solid basis for a licensing board complaint, even when the money dispute ends up in court. Before you file, see how to file a licensing board complaint. If the contractor changed the plans without asking you at all, see when a contractor changes the plans without asking.

Mistakes that hurt your case

These disputes are usually decided on what you can prove about who asked for what, and when. A judge or arbitrator will also look at whether your position is fair. Protect yourself by avoiding these mistakes.

  • Approving changes by text or on site without asking the price.
  • Assuming a fix the contractor offered was free.
  • Refusing to pay anything for extra work you clearly asked for and now use every day.
  • Signing a final invoice or an after-the-fact change order without reading it.

Your state's rules, with sources

Pick your state to see the rules that matter here, each linked to its official source.

What to gather

Tick things off as you collect them. Your list stays on this device only.

0 of 8 gathered

What to do, step by step

  1. 1

    List each disputed change

    For each extra charge, write down who asked for it, when, and whether a price was discussed. Attach the texts or emails.

  2. 2

    Ask for the backup

    Ask the contractor in writing for the change order, date and pricing behind each extra charge.

  3. 3

    Offer a fair amount for work you requested

    If you asked for a change, offering a reasonable price for it shows good faith. Dispute charges for work you never requested or that was already in the contract.

  4. 4

    Send your position in writing

    OwnersBack Dispute Prep can organize your records into a dated timeline, an evidence index and a demand letter you send in your own name. If the whole bill is far over the original price, see when the final bill is higher than the estimate.

  5. 5

    File a licensing board complaint if the rules were broken

    Many boards treat a missing written change order as a violation, and a complaint can bring the contractor to the table.

  6. 6

    Use small claims or arbitration if it doesn't settle

    If the dispute doesn't resolve, small claims court, or the arbitration your contract requires, is the usual next step.

When to talk to a lawyer now

  • The contractor has filed a lien or sued you for the extra charges.
  • The disputed changes add up to more than your state's small claims limit.
  • The changes affected structure, permits or code compliance.
  • Your contract has an arbitration or attorney fee clause.
Find a lawyer in your state

Turn this into a plan you can act on

We turn your paperwork, photos and messages into a dated timeline, an evidence index, a step-by-step plan and a demand letter. A person on our team checks every one.

Hiring someone new to finish the job? Check their bid for free before you sign.

Common follow-up questions

Do I have to pay for extra work I agreed to verbally?

Often, at least a reasonable amount, even if your state requires written change orders. Courts differ: Connecticut has been stricter in protecting homeowners, while Pennsylvania lets a contractor recover the reasonable value of its work. What you usually don't owe is a price far above what the work is worth.

Can a contractor charge for changes I never asked for?

Generally no. If you didn't request or approve the work, the contractor usually has a weak claim to be paid for it, especially in states that require signed change orders.

What should a change order include?

At a minimum, a description of the change, the added or reduced cost, any effect on the schedule, and both signatures with dates. California's rules also call for the effect on the payment schedule.

Is a text message a written change order?

It can help prove what was agreed, but many states call for a signed written change order, and a text may not meet that. Save every text either way.

The contractor says the change was needed to pass inspection. Do I have to pay?

Sometimes extra work is truly needed to meet code. Ask whether it was foreseeable when the contract was signed, because if the contractor should have priced it in, you may be able to dispute it. See who pays when a job fails inspection.

Laws and cases on this page

Each one was read on its source and checked on November 19, 2026.

  1. 1

    Statute · NY

    N.Y. Gen. Bus. Law § 771

    What it says

    In New York, a home improvement contract and every change to it must be in writing, signed by all parties, legible and in plain English, and you must get a signed copy before work starts. It must list the contractor's name, address, phone and any license number, approximate start and completion dates, the work and materials, the price, a lien notice, a notice about how your prepayments must be protected, any insurance covering the work, and, if progress payments are used, a schedule tied to stages of work. It must also tell you that you can cancel until midnight of the third business day after signing, except in certain emergencies you started.

    Keep in mind: New York only. This section lists what the contract must contain; what happens when a term is missing depends on the facts and on court decisions.

  2. 2

    Official guidance · CA

    CSLB, Home Improvement Contracts consumer guide

    What it says

    California's licensing board says home improvement jobs over $500 (labor and materials combined) must be in a written contract. When the contract is sold in your home, you get three business days to cancel, or five business days if you are 65 or older. It also says any change to the contract price must be made with a written change order, and the down payment cannot be more than $1,000 or 10 percent of the price, whichever is less.

    Keep in mind: This is a board consumer guide, not the statute text. The guide says the cancellation right does not apply if you negotiated the contract at the contractor's place of business, and the down payment limit does not apply to contractors with certain blanket bonds. Check the contract's cancellation notice and the current statute.

  3. 3

    Official guidance · CT

    Connecticut home improvement contract requirements (Department of Consumer Protection)

    What it says

    Connecticut's consumer protection agency says a home improvement contract and all changes to it must be in writing, include the contractor's registration number, the signing, start, completion and cancellation dates, the full work and price, and a notice of your right to cancel. Both sides must sign and date it, and you get a signed copy.

    Keep in mind: This is the agency's consumer guidance, not the statute text. It does not say what happens if a term is missing; that is governed by the Home Improvement Act and court decisions.

  4. 4

    Court decision · CT · Supreme Court of Connecticut

    Barrett Builders v. Miller, 215 Conn. 316, 576 A.2d 455 (1990)

    What it says

    A contractor installed kitchen cabinets and countertops under a written contract that left out key details and the required three-day cancellation notice, then sued the homeowner for the unpaid balance. The Connecticut Supreme Court held that a contract that does not meet the Home Improvement Act's requirements cannot be enforced against the homeowner, and the contractor cannot recover the value of its work through quasi-contract (unjust enrichment) either.

    Keep in mind: Connecticut case under Connecticut General Statutes section 20-429. Connecticut later recognized a bad faith exception (Habetz v. Condon, 1992), so a homeowner who acts dishonestly may still have to pay. Other states differ; some, such as Pennsylvania, let a contractor with a noncompliant contract recover the reasonable value of its work.

  5. 5

    Statute · PA

    73 P.S. § 517.7 (Home Improvement Consumer Protection Act, section 7)

    What it says

    In Pennsylvania, a home improvement contract is not valid or enforceable against the homeowner unless it meets the Act's requirements, such as being in writing and legible, showing the contractor's registration number, being signed by both sides, and listing approximate start and completion dates. The homeowner may cancel without penalty within three business days of signing, wherever the contract was signed.

    Keep in mind: Emergency work covered by the Unfair Trade Practices and Consumer Protection Law has its own rules.

  6. 6

    Court decision · PA · Supreme Court of Pennsylvania

    Shafer Electric & Construction v. Mantia, 626 Pa. 258, 96 A.3d 989 (2014)

    What it says

    Homeowners hired a contractor to build a garage addition under a contract that met only three of the 13 requirements of Pennsylvania's Home Improvement Consumer Protection Act. The Pennsylvania Supreme Court held that the contractor could still sue for the reasonable value of its work (quantum meruit), even though the noncompliant contract itself could not be enforced.

    Keep in mind: Pennsylvania case. It cuts against homeowners who hope a missing contract term means they owe nothing; other states (for example Connecticut, in Barrett Builders v. Miller) reach a different result.

  7. 7

    Court decision · CT · Supreme Court of Connecticut

    Habetz v. Condon, 224 Conn. 231, 618 A.2d 501 (1992)

    What it says

    A homeowner paid most of a $103,000 addition contract that lacked the required cancellation notice, then used that defect to avoid paying the rest and for extra work the homeowner had requested. The Connecticut Supreme Court held that a homeowner who acts in bad faith cannot use the Home Improvement Act to escape paying, and it defined bad faith as more than carelessness: it involves a dishonest purpose.

    Keep in mind: Connecticut case. Whether a homeowner acted in bad faith depends on the facts and is decided by the trial court. Other states may differ.

  8. 8

    Court decision · NY · New York Supreme Court, Appellate Division, Second Department

    Home Construction Corp. v. Beaury, 2017 NY Slip Op 02628 (App. Div. 2d Dept. 2017)

    What it says

    A contractor renovating a house worked without a signed contract, then stopped work with the job unfinished. The court dismissed the contractor's claim for more money because it did not prove the value of its work, and it awarded the homeowners $329,565 for the cost of completing the work and correcting defective work, measured by the fair and reasonable market price.

    Keep in mind: New York intermediate appellate decision that turned on its facts and the evidence each side presented. New York General Business Law section 771 requires home improvement contracts to be in writing, but the court noted a contractor may still try to recover the reasonable value of its work. Other states may differ.

Legal information, not legal advice

This page explains the law in general terms so you can understand your options. It isn't legal advice for your situation, and reading it doesn't create an attorney-client relationship. Laws change and differ by state, and the facts of your case matter. OwnersBack isn't a law firm. Before you sue, sign a settlement, or miss a deadline, talk to a licensed attorney in your state.