Sample check of a made-up proposal. This is exactly what you get for yours.

Check my proposal free →

Proposal check

Kitchen remodel, Rivera residence

  • Checked November 18, 2026 at 5:30 PM
  • PDF

4 required items to fix

Fix the items marked required, then check the updated file to earn the badge.

BidReady score

48

out of 100

Needs work

How much of the homeowner checklist this proposal covers. Required items count most.

4
Required to fix
13
Recommended
12
Covered

Your fix plan

12 of 29 covered

Start at the top. Required items stand between you and the badge.

  1. 1Lien waivers with paymentsHow the money moves · Missing
  2. 2Written change ordersWhen plans change · Missing
  3. 3Right-to-cancel noticePermits, notices and the owner's rights · Missing
  4. 4Payments tied to finished workHow the money moves · Weak
13 recommended improvements
  1. 5Insurance statedWho you are · Missing
  2. 6Subcontractors disclosedWho you are · Missing
  3. 7Allowances explainedWhat's included · Missing
  4. 8Hidden-condition termsWhat's included · Missing
  5. 9Change orders show price and timeWhen plans change · Missing
  6. 10Pricing for extrasWhen plans change · Missing
  7. 11Delays definedSchedule · Missing
  8. 12"Complete" definedWarranty and completion · Missing
  9. 13Materials namedWhat's included · Weak
  10. 14Total price and what changes itHow the money moves · Weak
  11. 15Start and finish datesSchedule · Weak
  12. 16State-required noticesPermits, notices and the owner's rights · Weak
  13. 17Fair dispute termsPermits, notices and the owner's rights · Weak

What we found

A clear kitchen remodel proposal with a good scope and a held-back final payment. It's missing the protections homeowners ask about most: written change orders, lien waivers and the right-to-cancel notice.

Business
Cedar & Pine Remodeling LLC
License no.
Oregon CCB #000000
Job state
Oregon
Total
$48,500
Deposit
$14,550 (30%) due at signing
Document
Proposal

Already strong

  • License, legal name and address are in the letterhead.
  • The scope lists the main work and what isn't included.
  • The final payment is held until the job is done.

Item by item

Who you are

2 of 4 covered
  • Insurance stated

    MissingRecommended

    Insurance isn't mentioned anywhere.

    How to fix it

    Name your insurance and offer the certificate before work starts.

    Suggested wording

    Contractor carries general liability insurance (carrier, limit $amount) and workers' compensation insurance or: is exempt because (reason). A certificate of insurance will be given to the Owner before work starts.

    Why it matters

    It's one of the top questions homeowners ask. Answering it on paper saves a call and builds trust.

  • Subcontractors disclosed

    MissingRecommended

    The plumbing and electrical subs aren't named.

    How to fix it

    List subcontracted trades and say you pay them.

    Suggested wording

    Subcontractors: trade: company name. Contractor is responsible for paying all subcontractors and suppliers on this job.

    Why it matters

    Unpaid subs can lien the house. Saying you pay them heads off the worry.

  • License or registration number

    The CCB number is printed under the business name.

    “Cedar & Pine Remodeling LLC · CCB #000000”· p. 1
  • Legal name and street address

    Legal name and a street address are in the letterhead.

What's included

3 of 6 covered
  • Allowances explained

    MissingRecommended

    A $6,000 tile allowance has no rule for what happens if the tile costs more.

    In your proposal · p. 1
    “Tile allowance: $6,000”

    How to fix it

    State what each allowance includes and how overages and credits work.

    Suggested wording

    Allowance for item: $amount for materials only / materials and installation, including / not including tax and delivery. If the Owner's choice costs more, the difference is added by signed change order; if less, the difference is credited.

    Why it matters

    An allowance that's too low looks cheap now and costs you trust at the overage.

  • Hidden-condition terms

    MissingRecommended

    Nothing says what happens if rot or old wiring turns up behind the walls.

    How to fix it

    Say you'll stop, show the owner and price it in writing before continuing.

    Suggested wording

    Hidden conditions: If concealed conditions (rot, mold, outdated wiring, structural damage) are found, Contractor will stop work in that area, show the Owner, and give a written change order with price and schedule impact before continuing, except work needed right away to make the area safe.

    Why it matters

    Setting the process up front turns the hardest conversation on a job into a routine change order.

  • Materials named

    WeakRecommended

    Cabinets are named, but the counters say only "quartz" with no brand or color.

    In your proposal · p. 1
    “Quartz countertops, standard edge”

    How to fix it

    Name brand and model, or the grade, for each main material.

    Suggested wording

    Materials: item, brand, model / color / grade. Substitutions only with the Owner's written approval.

    Why it matters

    Homeowners compare bids by what they get. Named materials make yours easy to compare.

  • Specific scope

    The scope lists demolition, cabinets, counters, tile, a sink move and two new circuits.

  • Exclusions listed

    Appliances and painting are listed as not included.

  • Cleanup and debris

    Daily cleanup and dumpster removal are included.

How the money moves

3 of 6 covered
  • Lien waivers with payments

    MissingRequired for badge

    No lien waivers are offered with any payment.

    How to fix it

    Promise a lien waiver with every payment.

    Suggested wording

    With each payment, Contractor will give the Owner a conditional lien waiver for that payment and unconditional waivers for earlier payments, from Contractor and from each subcontractor and supplier who worked on or supplied the job. Use the waiver forms Oregon requires, if any.

    Why it matters

    It answers the homeowner's fear of paying twice. Few bids offer it, so yours stands out.

  • Payments tied to finished work

    WeakRequired for badge

    The middle payment is due on a date, not when the cabinets are in.

    In your proposal · p. 1
    “40% due March 28”

    How to fix it

    Replace dates and intervals with stages a homeowner can see are done.

    Suggested wording

    Payment schedule: Each payment is due when the stage is complete: 1. Demolition complete: $amount. 2. Rough-in passed inspection: $amount. 3. Cabinets and counters installed: $amount. 4. Final (see completion): $amount. If you bill progress every two weeks, bill only for work completed in that period.

    Why it matters

    Homeowners have been burned by payments on a clock that kept coming while no one was on site. Milestones show you get paid for work, not time.

  • Total price and what changes it

    WeakRecommended

    One total price, but nothing says what can change it.

    In your proposal · p. 1
    “Total: $48,500”

    How to fix it

    State one total and what can change it.

    Suggested wording

    Contract price: $amount. It changes only through the allowances and unit prices above or a signed change order.

    Why it matters

    Homeowners compare totals first. A clear one keeps yours in the running.

  • Deposit within the state's limit

    A 30% deposit. Oregon has no statewide deposit limit.

    “Deposit: $14,550 (30%) due at signing”· p. 1
  • Payments in step with the work
  • Final payment held to completion

    The last 30% is due at completion.

When plans change

0 of 3 covered
  • Written change orders

    MissingRequired for badge

    Changes aren't mentioned. A verbal change could become a billing dispute.

    How to fix it

    Add a change-order clause.

    Suggested wording

    Changes: No change to the work, price or schedule is made without a written change order signed by the Owner and Contractor before the changed work begins.

    Why it matters

    Most invoice fights start with a change nobody wrote down. This protects your money as much as theirs.

  • Change orders show price and time

    MissingRecommended

    How to fix it

    Say each change order states price and schedule impact.

    Suggested wording

    Each change order states the work, the added or reduced price, and any change to the completion date.

    Why it matters

    A price and date on every change means no surprise at the final invoice.

  • Pricing for extras

    MissingRecommended

    No rate is given for extra work.

    How to fix it

    List your rate and materials markup.

    Suggested wording

    Extra work: labor $rate/hour; materials at cost plus 15%.

    Why it matters

    Pricing extras up front ends the after-the-fact negotiation.

Schedule

1 of 3 covered
  • Delays defined

    MissingRecommended

    How to fix it

    List excusable delays and promise written notice.

    Suggested wording

    Completion may be extended only for weather, permit or inspection delays, material shortages, Owner changes or hidden conditions. Contractor will tell the Owner in writing within 2 business days of any delay, with the new expected date.

    Why it matters

    It separates weather and permits from a crew on another job, so you aren't blamed for what you can't control.

  • Start and finish dates

    WeakRecommended

    "Start in March, about six weeks" with no dates.

    In your proposal · p. 1
    “Start in March, approx. 6 weeks”

    How to fix it

    Add a start date and a duration.

    Suggested wording

    Work will start on or about date and be substantially complete within number working days after start.

    Why it matters

    A date is what a homeowner plans their life around. It's often the deciding factor between close bids.

  • Point of contact and updates

    The project manager's name and weekly updates are listed.

Permits, notices and the owner's rights

1 of 4 covered
  • Right-to-cancel notice

    MissingRequired for badge

    There's no notice of the right to cancel.

    How to fix it

    Add the cancellation notice and the form, in the format your state requires.

    Suggested wording

    Owner's right to cancel: The Owner may cancel this home improvement contract within 1 business day, as Oregon law provides (ORS 701.310). Attach the Notice of Cancellation in the form Oregon requires.

    Why it matters

    Leaving it out can let the owner cancel later, and it signals a pressure sale.

  • State-required notices

    WeakRecommended

    Oregon's consumer notice isn't attached.

    How to fix it

    Attach each notice your state requires.

    Suggested wording

    Attached: the notices Oregon requires (see the official source below for the exact wording and format).

    Why it matters

    A missing required notice can cost you lien rights or let the owner void the contract.

  • Fair dispute terms

    WeakRecommended

    How to fix it

    Start with a talk, then mediation, before anything else.

    Suggested wording

    Disputes: The parties will first meet to resolve any disagreement, then try mediation in county before any other step. Each party pays its own costs unless a law says otherwise.

    Why it matters

    One-sided arbitration or fee clauses are what a homeowner's lawyer flags first.

  • Permits assigned

    The contractor pulls all permits.

Warranty and completion

2 of 3 covered
  • "Complete" defined

    MissingRecommended

    How to fix it

    Define completion.

    Suggested wording

    Completion: The job is complete when the final inspection passes, the Owner and Contractor do a walkthrough, and each item on the written punch list is done.

    Why it matters

    A clear finish line is how you get the final payment without a fight.

  • Workmanship warranty

    A one-year workmanship warranty.

    “1-year warranty on workmanship”· p. 1
  • Manufacturer warranties handed over

Oregon rules used

Deposit limit
No statewide limit on file
Cancellation window, every home improvement contract
1 business day
Cancellation window, contracts signed at the home
3 business days

Official source: Oregon CCB, Consumer Tools; CCB Guide to Home Improvement Contracts; ORS Chapter 701 (2025 edition)

Payment timing and the deposit are checked by rule, not judgment.

Suggested wording is a starting point, not legal advice. Have your attorney review your contract.